12/06/2025
Busby Construction began to hook up the sewer connection this week. Originally we were going to have just a holding tank and have it pumped on a regular schedule but by code, that was not allowed. A delay in the start of the entire project was because the airport was going to bring in the utilities. Once that began, we started. Only to find out that the engineer for both the airport and for ourselves was incompetent and never put two and two together treating both projects separately and only designed to the lot before us, never considering our lot. The airport corrected the oversight but this delayed the schedule even more adding costs and time. This is the final step of this project. Busby will be back next week to construct inverts and final inspection from the town. Once completed, the restroom will be operational and permanent CofO can be issued.