🚧 Schlather Ranch Project Update
Progress continues at Schlather Ranch as the community moves closer to its next major milestones.
Recent work has included substantial progress on the water infrastructure, with the water main reported at 99% complete and water services at 95% complete. Crews have also continued concrete flatwork, drainage improvements, utility conduit work, roadway preparation, and curb installation throughout the development.
Although heavy rain temporarily slowed activity during the week of July 13–17, the next phase of work is already moving forward. Upcoming priorities include installing the first lift of road base, continuing concrete flatwork, advancing curb work along Elizabeth and Sylvia, and verifying that lots on the north end are cleared and ready for continued development.
A special thank you to D&D Contractors, Inc. and the entire project team for their continued hard work, flexibility, and dedication as Schlather Ranch takes shape.
Stay tuned for more progress updates! https://kingfishtx.com