11/01/2026
Last week we finished the access road, so we can now get to the site and begin vertical construction. We also held a pre-construction meeting with the Core Electrical team, and Xcel gas lines have been pulled into the building. The sewer lines are complete, while electrical work is still underway. Storm-water drain pipes have been installed from the building out to the exterior. Deck-support panels are in place around the perimeter to mount the shield sheets that will receive the concrete slab pour. Over all it is progressing with few delays. We are working with the GC on the revised schedule, we will have it next week.