10/30/2026
Progress continues at Ulery’s Lake as we near completion of the foundation phase!
Brandon walks us through the latest developments on site, including the installation of a 12-inch-thick mat slab foundation, ongoing waterproofing, and reinforcement work on the remaining foundation walls.
With double-wall rebar installation nearing completion, the team is preparing for the next concrete pour in the coming weeks.