๐น Construction Update โ Aura Ra | 28.09.2026 ๐น
Aura Ra continues to rise. Over the past month, the construction team has made significant progress across both blocks โ from completing major structural works to advancing blockwork across multiple levels of the development.
๐ Block A
One of the key milestones has been the completion of the main concrete works on the 10th floor. The slab, beams, and columns have been completed, and construction is now moving up to the roof level.
At the roof level, the slab and beams have been completed, including reinforcement, formwork, and concrete pouring. The team is currently working on the reinforcement and formwork of the roof-level columns, preparing the structure for the next stage.
At the same time, blockwork is progressing actively. Works have been completed on the 1st, 2nd, 3rd, 5th, 6th, 7th, and 8th floors, while work on the 4th and 9th floors is currently ongoing.
๐ Block B
Construction at Block B is also moving up to the next levels.
On the 3rd floor, the main works on the slab and beams have been completed โ from formwork and steel reinforcement to concrete pouring. De-shuttering is currently underway, along with preparations for the columns.
Blockwork on the 1st floor has also been completed.
Step by step, Aura Ra Paje is moving from individual construction stages towards a clearly defined structure of the future development.
More floors, new milestones, and plenty of progress are still ahead. ๐๏ธ๐ด
Aura Ra | Paje, Zanzibar