15/09/2026
Here's the progress update for August:
• Soil excavated and removed: 347,750 m³
• Piles drilled: 2,360 piles
• Structural concrete poured: 28,768 m³
• Building A1: Work continues on the basement slab structure.
• Building A2.2, Zone 1: Work continues on the 4th-floor slab structure.
• Building A2.2, Roof Zone: Planter box casting is in progress.
• Building A3.1: Reinforcement and post-tensioning system installation is in progress for the 5th-floor slab.
• Building A3.2: Work continues on the basement structures.
• Building A4: Work on the stair structure continues.
• Building A5: Texture painting has commenced on the 5th floor. MEP works continue on the 4th floor. Wall plastering is in progress on the 3rd floor.
• Building BM1: Foundation works are ongoing.
• Building BM2, Zone 2: Scaffolding and formwork installation are in progress for the 1st-floor slab.
• Building ME1: Foundation and reinforced concrete wall works are ongoing.
• Building B1: Pile drilling continues.
• Building B8: Work continues on the basement floor slab and reinforced concrete walls.
• Building B9: Foundation works are ongoing.