🚨 **MahaRERA BIG UPDATE: 4-Month Automatic Extension for Eligible Projects**
MahaRERA **Order No. 66/2026**, dated **07.08.2026**, provides an automatic **4-month extension** to specified registered real estate projects under **Section 6 of RERA, 2016**, on Force Majeure grounds.
But does every project get the benefit?
**No.**
The key conditions are:
✔ Original/Revised/Extended Completion Date falls on or after **28.02.2026**
✔ Project registered **before 01.08.2026**
❌ Projects registered on or after **01.08.2026** are excluded.
**Is a separate application required?**
No. The four-month extension is granted automatically.
**Will MahaRERA update the portal?**
Yes. The Order directs the Registration and IT Cell, MahaRERA to update the records and portal.
**Does this automatically remove all buyer delay claims?**
No. The regulatory extension should not automatically be treated as changing every contractual right under an Agreement for Sale. Buyer-specific issues such as possession, interest, compensation or refund need separate examination.
**For promoters:** Check your registration date and current completion date.
**For homebuyers:** Check the MahaRERA record, Agreement for Sale and actual project status before drawing conclusions.
✨ **योग्य ज्ञान, उज्ज्वल भविष्य — PIREE INDIA सोबत.**
👉 Follow PIREE INDIA for simplified RERA updates and real estate awareness.
**Disclaimer:** ⚠️ This post is for educational and awareness purposes only. The information is based on **MahaRERA Order No. 66/2026, MahaRERA/Secy/388/2026, dated 07.08.2026**. It is not legal, financial or investment advice. Verify the latest official MahaRERA records and consult a qualified professional for project-specific matters.
Official MahaRERA: [MahaRERA](https://maharera.maharashtra.gov.in/?utm_source=chatgpt.com)
Read our blog on Piree India : Link in Comment
Source: MahaRERA Order No. 66/2026.