Land Matters, but Electricity Matters Much More.
About seven months ago, I was approached by a company in the Energy & Utilities sector looking for a substantial plot of land (approximately 50 dunams, or 12.5 acres) in central Israel to develop a data center.
I identified a suitable site, and the company began its due diligence process. However, in July of this year, the Israel Electricity Authority ordered a 140-day freeze on processing new grid connection applications, following unprecedented demand totaling approximately 27,000 MW, roughly equivalent to the peak electricity demand of Israel's entire private sector.
I'll return to my client shortly.
Last week, a new proposed regulatory framework for electricity allocation was published, with the following key provisions:
Proposed allocation of 1,300 MW for new data centers, including 300 MW designated for local consumers.
Maximum grid connection capacity of 200 MW per new data center.
Financial guarantees of up to NIS 2 million per MW.
Option for self-generation using renewable energy and energy storage, without automatic priority for grid connection.
This is still a draft decision subject to public consultation. The emerging regulatory framework could significantly influence the future of the industry and the development of data center and AI infrastructure in Israel.
In the coming days, I will join fellow members of the I.D.C.A. (Israel Data Center Association) to formulate a joint professional industry position on the proposed framework.
The implications for the commercial real estate market are profound.
A large plot of land in a prime location is no longer enough.
Power availability, grid connection capacity, planning feasibility, and demonstrated financial strength will become the decisive factors in determining whether projects can move forward.
And back to my client.
Like many others, the company is waiting for the final regulatory decision before determining its next steps...