Most people planning a renovation count the weeks on a calendar. That's where it starts going wrong.
Four things come out of a Quebec construction schedule before anyone picks up a tool:
1. The permit. Drawings and fees first, then the city assesses it. Weeks, sometimes longer.
2. The CNESST notice. Ten days' written notice before work can begin on site. Longer for big jobs.
3. Statutory holidays. Ten in construction, eight of them outside the holiday break.
4. The construction holidays. Two weeks in winter, two in summer. The industry stops.
So a job you planned from January to December has about 44 working weeks, not 52.
Eight weeks you never had, and you find out in month nine.