02/10/2026
Zephyra Residences has reached 55.89% overall project completion, continuing to progress in line with the planned schedule. All major structural works, including the foundations, residential structure and roof, are now fully completed. Masonry has reached 75%, while internal utilities have progressed to 44%.
During September, construction continued across multiple areas of the project, with further progress in masonry, plastering, waterproofing, glazing and engineering systems. Internal utilities, electrical and plumbing works, HVAC and firefighting systems are advancing alongside architectural finishing works across apartments and common areas.
The project is now firmly progressing through its architectural, MEP and finishing stages, with 319 days remaining against the current baseline completion date.