Bluewaters Bay | Construction Progress | Q3 2026
Meraas’ Bluewaters Bay development has reached 40.88% construction progress according to internal project tracking for September 2026, while RERA inspections recorded 36.97% in late August. Both towers are approaching structural completion, with façade, MEP and interior works progressing ahead of the anticipated March 2027 handover.
Key Highlights 🔍
* Overall construction progress reached 40.88% in September 2026, up from 31% in June.
* Tower 1 structural works surpassed Level 50 of 53 storeys.
* Tower 2 structural works surpassed Level 40 of 44 storeys.
* Façade, MEP installations and interior fit-outs are progressing across both towers.
* Development comprises 1–4 bedroom apartments and limited 5-bedroom penthouses.
* Community amenities include a landscaped podium promenade, elevated garden, fitness zones and tennis court.
* Anticipated handover is expected to begin around March 2027.
➡️💡 : Bluewaters Bay is advancing towards delivery within one of Dubai’s established waterfront and marina-connected locations. Its dual access to Sheikh Zayed Road and Dubai Marina, combined with direct waterfront positioning and panoramic views, differentiates the development through connectivity and residential setting. Progress across both towers and the commencement of interior works mark the transition towards the final stages of construction, bringing the project closer to adding premium waterfront housing to the Bluewaters district.