12/04/2020
PELLA CONSTRUCTION UPDATE:
Work Recently Completed:
1. Drywall has been installed in units 15-18
2. Units 13 and 14 ready for shingles
3. Floors for units 3-8 have been poured and covered with winter blankets
4. Unit 22 has been painted ready for finish items to be installed
5. Ceramic tile floor base has been set in units 19-22
6. Garage door seals have been installed
7. Ductwork has been sealed in units 15-18
8. Exterior walls have been insulated and have a vapor barrier installed
Work Currently in Progress:
1. Siding being installed on unit 19-22
2. Painting in unit 21
3. Ceramic tile is being installed in unit 22
4. HVAC duct grill is being installed in unit 22
5. Units 15-18 exterior columns are being built out for finish siding and stone
Work Scheduled in the Next Two Weeks:
1. Gas Line gets installed
2. Siding, soffit, and Fascia of units 19-22
3. Pour stoops on units 3-14
4. Units 11 and 12 framings to continue
5. Start Clubhouse foundation
6. Units 15-18 attics to get blown insulation
7. Units 13 and 14 to start shingles
8. Mechanical rough-in for units 13 and 14.
9. Basements walls to be insulated on units 15-18