A contractor committed to finishing the flooring by August 1.
It was about 300 square feet. He had roughly 10 days. That is not an impossible job.
So I did what you are supposed to do. I kept following up. Every time, the answer was the same. It was handled. He was going back that day. It would be done.
The day my tenants moved in, there were still several pieces of flooring missing and no trim installed.
The work had not changed. The situation had.
An empty unit is a scheduling problem. You line up the contractor, you give them access, you wait. Once a family is carrying boxes through the door, it becomes something else entirely. Every return visit now has to be coordinated around people who live there. Every loose plank and every missing piece of trim is something my resident sees before they have finished unpacking.
I do not think the takeaway is just to find a better contractor. The takeaway is that a promise is not progress.
"I'm going back today" is not the same as flooring that is actually installed. And the moment the tenant has the keys, that gap stops being the contractor's problem and becomes mine.
Now I manage to what is done on site, not to what I was told would be done.